WEEK- 5 Oct - 19
Safety is a major issue across global construction Industries. People here at Lennar Company are much concerned about safety. They have mandatory safety orientation for all visitors. Making every visitor aware about every hoarding instruction on site is part of safety procedure. Safety instruction boards are installed on every location. As for the workers, PPE compulsory. Fire extinguisher on every floor is active. On top of that, all the material on the site have to be stored properly is one of the prime concerns for the LMC.

Safety tie is installed on every part of the building edges.
Worker working near to the edge of the floor is required to tie himself with this safety belt.


The procedure is called the ABC procedure,
where: ABC refers to:
A is ‘Ankle point’
B is for ‘Body harness’
C is ‘Connection to devices’
Apart from onsite safety measure, they have designated area for the all the safety boards and safety equipment orientation, with the med-plus emergency kit. The safety area contains any working subcontractor’s information, how to use and treat the chemical substances available on the site and direction for the nearest hospital.
​
This is what the LMC do when some incident happens on the site with any individual:
-
Assist the victim with med plus kit
-
Call 911 for the rescue
-
Refer the safety code of the victim and call the supervisor under whom the victim is working to report.


25th Floor: Construction is continuing on the new floor, 25. Columns are casted on 25A and post tension cables have been laid on 25B.
24th Floor: Reshores are installed on this level to support the slab on top.
23rd and 22nd Floor: Plumbing works are progressing, and pipes have been installed. We could see pipes for the tubs and toilets installed. Materials for exterior sheathings were present on the floor. Hopefully they will be starting the sheathing works soon.
21st and 20th Floor: Staircase roofing construction was completed. Exterior water proof painting was in process during our visit.
19th and 18thFloor: Temporary lights have been fixed on the 19th level. Plumbing work for 18th floor is almost completed.
17th and 16th Floor: Interior wall steel framing was completed and Looping light is installed till 17th floor for making the distinction from the stair.
15th, 14th and 13th Floor: Exterior Sheathings have been installed. Plumbing works have made a great progress this week.
12th and 11th Floor: Main electrical line works almost completed. That is supposed to energize the entire panel. HVAC system works are progressing at these levels. Pipes for the kitchen and sprinklers are set in position.
10th, 9th and 8th Floor: The mistake on level 9 was not fixed yet. More electrical progress seen during this week on these levels. Fiber glass to be installed for insulation purposes is present on the 8th level. A ventilation fan is fixed on level 8 for removal of exhaust gases.
Below Level 7: Most of the walls are completed on level 7. Dry wall works are almost completed. Doors are installed on level 5. The curtain walls seemed to be covered with transparent polythene cover for protection during painting works on the floors. Progress with the corridors are also visible. The Cleaning works on the second work is continuing. The tiles on the rest rooms are laid and seemed different because that is according to a different scheme.
SAFETY
FLOOR PROGRESS